Sewer Call Off Maintenance Phase 1
Project Title |
Sewer Call Off Maintenance Phase 1 |
Project ID |
AA-DOM/13-14/M/1542-4.07/G |
Project Brief |
The scope of the project is to upgrade the sewer pipeline within the following catchment areas in Doha. PS 1 (Zone 1) PS 5 & 31 (Zone 13) PS 6 (Zone 15) PS 7 (Zone 27) PS 10 (Zone 25) PS 11 (Zone 25) The scope of works mainly is for the following:
|
Commencement Date |
05 January 2014 |
Client | Public Works Authority (Ashghal) |
Year completed: | 2016-10-31 |
Project status: | completed |
Price: | QR 71,460,409.00 |