Design and Construction of Lateral Interceptor Sewer LIS 01
Project Title |
INNER DOHA RE-SEWERAGE IMPLEMENTATION STRATEGY Design and Construction of Lateral Interceptor Sewers (LIS-01) |
Project ID |
IA 13/14 C 39 M |
Project Brief |
The Works addressed by the Project comprises the design, execution, completion, and remediation of defects of the LIS network in Central Doha which connects to the MTS at seven locations. The Works include the design, procurement, construction, testing, completion and defects correction of the following:
The Works comprises the design, construction, testing, commissioning and handing over of the following works: 1.LIS-01sewerupstreamofMTS-01workshaftWS11 2.LIS-01sewerupstreamofMTS-01accessshaftAS13 3.LIS-01sewerupstreamofMTS-01workshaftWS1 4.LIS-01sewerupstreamofMTS-01accessshaftAS01 5.LIS-01sewerupstreamofMTS-01accessshaftAS02 6.LIS-01sewerupstreamofMTS-01workshaftWS4 7.LIS-01sewerupstreamofMTS-01accessshaftAS03 TheLIS-01 Contract is to be constructed by means of microtunnelling and pipejacking within the public Right of Way (ROW), buffer zones adjacent to the ROW and al located utility corridors. The Contractor is responsible for utilizing sufficient microtunnelling and pipejacking equipment, compliant with the specifications, to achieve the completion milestones. |
Commencement Date |
18-September-2016 |
Client | Public Works Authority (Ashghal) |
Year completed: | 2020-02-05 |
Project status: | ongoing |
Price: | 1,084,607,299.34 |